JE Dunn Construction has been selected by the Metropolitan Airports Commission as construction manager-at-risk for the $480-million Terminal 1 Boiler and Chiller Replacement and Energy Management Center expansion project at Minneapolis-St. Paul International Airport, the latest major investment in an ongoing $1.47 billion multi-year modernization of the airport.
The project would upgrade the central utility plant that provides heating and cooling to Terminal 1 and its parking structures. Originally brought online with Terminal 1 in the early 1960s, the facility operates around the clock and has reached the end of its useful life, says Bill Igel, vice president and project director at JE Dunn.
The work is expected to include replacement of heating and cooling systems, expansion of the Energy Management Center to accommodate new equipment and capacity, and improvements to adjacent areas of Concourse C.
“Our priority is careful planning, transparent communication and a phased execution that ensures the airport remains fully operational throughout construction,” said Jeff Callinan, JE Dunn vice president and Minneapolis office leader, in a news release.
The firm will join the commission and the design team during preconstruction to provide constructability reviews, cost estimating, scheduling, phasing, logistics planning, risk management and long-lead equipment procurement support. The construction manager-at-risk delivery model brings the contractor into the design process early and establishes guaranteed maximum prices as project phases advance, JE Dunn says.
“One of the project’s most significant engineering and construction challenges will be navigating space constraints within a fully operational facility. The existing Energy Management Center is boxed in by terminal infrastructure, leaving insufficient room to install the larger replacement boilers and chillers,” Igel says.
“Accommodating the new equipment will require expanding the … building, a change that will have a ripple effect on the surrounding terminal,” he adds. “Six active gate hold areas on Concourse C, serving gates C6-C11, will have to be demolished and rebuilt with larger footprints to accommodate the expansion. The Energy Management Center and concourse work will be carefully phased to keep gates operational and minimize disruptions throughout construction.”
Throughout the multiyear effort, the central plant must remain operational around the clock.
“Our teams will rely on incredibly precise sequencing and coordination to replace critical infrastructure while maintaining uninterrupted heating and cooling,” Igel says. “All work will take place alongside active airport operations, with the safety and experience of passengers and airport staff remaining a top priority throughout construction.”
The planned improvements are intended to improve efficiency, sustainability and operational resilience while contributing to commission goals to reduce greenhouse gas emissions by 80% and water use per passenger by 15% by 2030, with a long-term goal of net-zero emissions by 2050, JE Dunn says.
The project follows more than a decade of major airport construction and modernization work.
The commission finished up its $600-million Terminal 1 operational improvements program in 2025. The work expanded and modernized pre-security areas, including ticketing, security checkpoints and baggage claim. Morcon Construction Co. completed the final phase, a $24.4-million project that included baggage claim and ticket lobby improvements and curbside canopy repairs and lighting upgrades. Earlier phases also involved Morcon and Sheehy Construction Co.
Also completed in 2025 was the $242-million airport modernization program, a partnership between the airport commission and Delta Air Lines that renovated six Terminal 1 concourses and about 75 Delta gate areas. The commission contributed $182.5 million and Delta kicked in $60 million. JE Dunn was contractor for Terminal 1 modernization work, a project that included new flooring, ceilings, wall finishes, lighting, technology, seating, gate podiums and other improvements.
Work continues on the $305-million Concourse G expansion, which is set to add nearly 157,000 sq ft, expand gate seating and international-arrivals capacity, and add concessions, restrooms and other improvements. Sheehy Construction Co. was awarded the primary construction contract for the project in September 2024. Completion is expected in 2028.