Lake Marion Restoration
Severn, Md.
Award of Merit
Submitted by: BayLand Consultants & Designers Inc.
Owner: Provinces Civic Association
Lead Design Firm and Civil Engineer: BayLand Consultants & Designers Inc.
General Contractor: Pay Dirt
Nonprofit Grantors: Seven River Association and Arundel Rivers Foundation
Subcontractors: Ashton Manor Environmental; Xylem US Inc; AB Consultants Inc.
The project culminated a 20-year community-led effort to restore the 3-acre detention pond that had sustained diminished ecological function. Removal of accumulated sediment restored the lake to its historical depth and reestablished a permanent pool up to 8 ft deep. Forebays were constructed at primary inflow points to capture sediment and reduce long-term maintenance requirements. A 20-ft to 30-ft-wide aquatic bench constructed around the lake perimeter and planted with native vegetation provides shallow water habitat, promotes nutrient uptake and transformation, stabilizes slopes and enhances overall ecological diversity. The bench also functions as a buffer to intercept sediment and pollutants prior to entering the main pool.
Reconstruction of the embankment required installation of a 14-ft-deep cutoff trench compacted to 95% to meet dam safety requirements. A temporary groundwater control system reduced inflow to normal levels, allowing for proper placement and compaction of materials while maintaining construction progress.